Installation Procedure For The Improved 377-2167 Water Lines Gp {1380} Caterpillar


`
Installation Procedure For The Improved 377-2167 Water Lines Gp {1380} [REHS8233]
COOLING SYSTEM
LINES GP-WATER
Installation Procedure For The Improved 377-2167 Water Lines Gp {1380}
1.1. Introduction
2.1. Installation Procedure
Engine:
G3520B (S/N: GLF1100-UP)
Petroleum Engine:
G3520B PETROLEUM (S/N: TPC140-140,1002-UP)

Introduction

Use this procedure to install the additional mounting clips on the 377-2167 Water Lines Gp .

Installation Procedure




    Illustration 1g03494142

    (1) 208-6270 Clamps

  1. Remove clamps (1) .



    Illustration 2g03495358

    (2) 6V-1581 Clips

    (3) 6V-1582 Clips

    (4) 0L-1143 Bolts

    (5) 9X-6458 Hard Washers

    (6) 9S-8752 Nuts

    (7) 205-6716 Spacers

  1. Install clips (2) and (3).

  1. Attach two pairs of clips (2) and (3) using one bolt (4), two washers (5), and one nut (6). Install one spacer (7) in between the pair of clips.



    Illustration 3g03495500

    (2) 6V-1581 Clip

    (3) 6V-1582 Clip

    (5) 9X-6458 Hard Washers

    (6) 9S-8752 Nuts

    (8) 4P-9029 Bracket

    (9) 0S-1591 Bolt

    (10) 0S-1619 Bolt

    (11) 8B-2026 Spacer

  1. Install one clip (2) and one clip (3).

  1. Install bracket (8). Attach bracket (8) to clips (2) and (3) using one bolt (9), two washers (5), and one nut (6) .

  1. Attach bracket (8) to the oil fill elbow using one bolt (10), one washer (5) and one spacer (11) .

Information System:

2013/10/31 Improved Water Lines Group For Certain G3520B Engines {1380}
2013/11/13 Cylinder Head Gasket Torque Procedures for Certain 3500 Engines {1100, 1124}
2013/11/12 Cylinder Head Gasket Torque Procedures for Certain3500 Machine Engines {1100, 1124}
C32 Marine Generator Set Maintenance Interval Schedule
C9 Petroleum Engine Fluid Recommendations
C9 Petroleum Engine Refill Capacities
Inspection Criteria for MMUs Experiencing Load Cell - CM Errors{4480}
XQC1200 Power Module Before Starting Engine
XQC1600 Power Module Electronic Modular Control Panel 4 (EMCP 4)
Retrofit SCR Aftertreatment Catalyst (SCR) - Clean/Inspect
C7 Petroleum Engine Maintenance Interval Schedule
XQC1600 Power Module Plate Locations and Film Locations
C13 and C15 Generator Sets Refill Capacities
Three60 Precision Control System Configuration Parameters
12M Series 3, 140M Series 3, 160M Series 3, 140, 150 and 160 Motor Graders Diagnostic Trouble Codes
C4.4 Industrial Engine Coolant (ELC) - Change
2014/01/13 New Jacket Water Heater Groups Are Used on Certain 3500 Engines {1383}
794 AC, 796 AC, and 798 AC Off-Highway Truck Electronic Control System Diagnostic Trouble Codes
3512B and 3516B Generator Set Engines with Dynamic Gas Blending Water Temperature Regulator
2013/12/10 A New Cable Assembly for the Powered Access Stairway Is Now Used on Certain Off-Highway Trucks {7254}
Procedure for Removing and Installing the Exhaust Cooler (NRS) on All Tier 4 C15 and C18 Engines {108C, 108G}
3512B and 3516B Generator Set Engines with Dynamic Gas Blending Radiator
2013/10/24 New Software for the Turbocharger Protection Strategy on the C4.4 Engine {1052, 1920}
3512B and 3516B Generator Set Engines with Dynamic Gas Blending Air Shutoff